290 Highland Ave: We’re Getting Framed!

    We are back on site today to see how things are coming along and we got some great news. We are right on schedule! Over the last two weeks, our team finished up laying the second-floor deck and secured it with a smooth layer of concrete. Completing the second-floor deck finished up our steel stage and gave way to starting framing.

    What you see pictured here is what will be the second floor. The second floor will house three units and will be the lowest level of living. That’s right- no ground level units. We are very excited about that! Over the next four weeks, you will see the third and fourth (penthouse) levels under construction. The third and fourth floors will house two units. The area where the green van is parked will be the car port.

    The goal is to have the entire building framed and sealed before the weather gets too cold. That way our contractors can work on interior projects through the winter and won’t freeze. Things are taking shape! We can’t wait to deliver this project to you. If you are interested in any of our units, please contact us for more information.

    If you happen to stop by the site, we’d love to see you! Tag us on Instagram: @localpropshop and use #290highland

    We’d love if you threw us a like on Facebook.

    That’s all for now, have a great weekend!

    Trackback from your site.

    Leave a Reply